Annex I – Nuclear-related measures
A. GENERAL
1. The sequence of implementation of the commitments detailed in this Annex is specified in Annex V to the Joint Comprehensive Plan of Action (JCPOA). Unless otherwise specified, the durations of the commitments in this Annex are from Implementation Day.
B. ARAK HEAVY WATER RESEARCH REACTOR
2. Iran will modernise the Arak heavy water research reactor to support peaceful nuclear research and radioisotopes production for medical and industrial purposes. Iran will redesign and rebuild the reactor, based on the agreed conceptual design (as attached to this Annex) to support its peaceful nuclear research and production needs and purposes, including testing of fuel pins and assembly prototypes and structural materials. The design will be such as to minimise the production of plutonium and not to produce weapon-grade plutonium in normal operation. The power of the redesigned reactor will not exceed 20 MWth. The E3/EU+3 and Iran share the understanding that the parameters in the conceptual design are subject to possible and necessary adjustments in developing the final design while fully preserving the above-mentioned purposes and principles of modernisation.
3. Iran will not pursue construction at the existing unfinished reactor based on its original design and will remove the existing calandria and retain it in Iran. The calandria will be made inoperable by filling any openings in the calandria with concrete such that the IAEA can verify that it will not be usable for a future nuclear application. In redesigning and reconstructing of the modernized Arak heavy water research reactor, Iran will
maximise the use of existing infrastructure already installed at the current Arak research
reactor.
4. Iran will take the leadership role as the owner and as the project manager, and have responsibility for overall implementation of the Arak modernisation project, with E3/EU+3 participants assuming responsibilities regarding the modernisation of the Arak reactor as described in this Annex. A Working Group composed of E3/EU+3 participants will be established to facilitate the redesigning and rebuilding of the reactor. An international partnership composed of Iran and the Working Group would implement the Arak modernisation project. The Working Group could be enlarged to include other countries by consensus of the participants of the Working Group and Iran. E3/EU+3 participants and Iran will conclude an official document expressing their strong commitments to the Arak modernisation project in advance of Implementation Day which would provide an assured path forward to modernise the reactor and would define the responsibilities assumed by the E3/EU+3 participants, and subsequently contracts would be concluded. The participants of the Working Group will provide assistance needed by Iran for redesigning and rebuilding the reactor, consistent with their respective national laws, in such a manner as to enable the safe and timely construction and commissioning of the modernised reactor.
5. Iran and the Working Group will cooperate to develop the final design of the modernised reactor and the design of the subsidiary laboratories to be carried out by Iran, and review conformity with international safety standards, such that the reactor can be licensed by the relevant Iranian regulatory authority for commissioning and operation. The final design of the modernised reactor and the design of the subsidiary laboratories will be submitted to the Joint Commission. The Joint Commission will aim to complete its review and endorsement within three months after the submission of the final design. If the Joint Commission does not complete its review and endorsement within three months, Iran could raise the issue through the dispute resolution mechanism envisaged by this JCPOA.
6. The IAEA will monitor the construction and report to the Working Group for confirmation that the construction of the modernised reactor is consistent with the approved final design.
7. As the project manager, Iran will take responsibility for the construction efforts. E3/EU+3 parties will, consistent with their national laws, take appropriate administrative, legal, technical, and regulatory measures to support co-operation.
E3/EU+3 parties will support the purchase by Iran, the transfer and supply of necessary materials, equipment, instrumentation and control systems and technologies required for the construction of the redesigned reactor, through the mechanism established by this JCPOA, as well as through exploration of relevant funding contributions.
8. E3/EU+3 parties will also support and facilitate the timely and safe construction of the modernized Arak reactor and its subsidiary laboratories, upon request by Iran, through IAEA technical cooperation if appropriate, including but not limited to technical and financial assistance, supply of required materials and equipment, state-of-the-art instrumentation and control systems and equipment and support for licensing and authorization.
9. The redesigned reactor will use up to 3.67 percent enriched uranium in the form of UO2 with a mass of approximately 350 kg of UO2 in a full core load, with a fuel design to be reviewed and approved by the Joint Commission. The international partnership with the participation of Iran will fabricate the initial fuel core load for the reactor outside
Iran. The international partnership will cooperate with Iran, including through technical assistance, to fabricate, test and license fuel fabrication capabilities in Iran for subsequent fuel core reloads for future use with this reactor. Destructive and non-destructive testing of this fuel including Post-Irradiation-Examination (PIE) will take place in one of the participating countries outside of Iran and that country will work with Iran to license the subsequent fuel fabricated in Iran for the use in the redesigned reactor under IAEA monitoring.
10. Iran will not produce or test natural uranium pellets, fuel pins or fuel assemblies, which are specifically designed for the support of the originally designed Arak reactor, designated by the IAEA as IR-40. Iran will store under IAEA continuous monitoring all existing natural uranium pellets and IR-40 fuel assemblies until the modernised Arak reactor becomes operational, at which point these natural uranium pellets and IR-40 fuel assemblies will be converted to UNH, or exchanged with an equivalent quantity of
natural uranium. Iran will make the necessary technical modifications to the natural uranium fuel production process line that was intended to supply fuel for the IR-40 reactor design, such that it can be used for the fabrication of the fuel reloads for the modernised Arak reactor.
11. All spent fuel from the redesigned Arak reactor, regardless of its origin, for the lifetime of the reactor, will be shipped out of Iran to a mutually determined location in E3/EU+3 countries or third countries, for further treatment or disposition as provided for in relevant contracts to be concluded, consistent with national laws, with the recipient party, within one year from the unloading from the reactor or whenever deemed to be safe for transfer by the recipient country.
12. Iran will submit the DIQ of the redesigned reactor to the IAEA which will include information on the planned radio-isotope production and reactor operation programme. The reactor will be operated under IAEA monitoring.
13. Iran will operate the Fuel Manufacturing Plant only to produce fuel assemblies for light water reactors and reloads for the modernized Arak reactor.
C. HEAVY WATER PRODUCTION PLANT
14. All excess heavy water which is beyond Iran's needs for the modernised Arak research reactor, the Zero power heavy water reactor, quantities needed for medical research and production of deuterate solutions and chemical compounds including, where appropriate, contingency stocks, will be made available for export to the international market based on international prices and delivered to the international buyer for 15 years. Iran's needs, consistent with the parameters above, are estimated to be 130 metric tonnes of nuclear grade heavy water or its equivalent in different enrichments prior to commissioning of the modernised Arak research reactor, and 90 metric tonnes after the commissioning, including the amount contained in the reactor.
15. Iran will inform the IAEA about the inventory and the production of the HWPP and will allow the IAEA to monitor the quantities of the heavy water stocks and the amount of heavy water produced, including through IAEA visits, as requested, to the HWPP.
D. OTHER REACTORS
16. Consistent with its plan, Iran will keep pace with the trend of international technological advancement in relying only on light water for its future nuclear power and research reactors with enhanced international cooperation including assurances of supply of necessary fuel.
17. Iran intends to ship out all spent fuel for all future and present nuclear power and research reactors, for further treatment or disposition as provided for in relevant contracts to be concluded consistent with national laws with the recipient party.
E. SPENT FUEL REPROCESSING ACTIVITIES
18. For 15 years Iran will not, and does not intend to thereafter, engage in any spent fuel reprocessing or spent fuel reprocessing R&D activities. For the purpose of this annex, spent fuel includes all types of irradiated fuel.
19. For 15 years Iran will not, and does not intend to thereafter, reprocess spent fuel except for irradiated enriched uranium targets for production of radio-isotopes for medical and peaceful industrial purposes.
20. For 15 years Iran will not, and does not intend to thereafter, develop, acquire or build facilities capable of separation of plutonium, uranium or neptunium from spent fuel or from fertile targets, other than for production of radio-isotopes for medical and peaceful industrial purposes.
21. For 15 years, Iran will only develop, acquire, build, or operate hot cells (containing a cell or interconnected cells), shielded cells or shielded glove boxes with dimensions less than 6 cubic meters in volume compatible with the specifications set out in Annex I of the Additional Protocol. These will be co-located with the modernised Arak research reactor, the Tehran Research Reactor, and radio-medicine production complexes, and only capable of the separation and processing of industrial or medical isotopes and non-destructive PIE. The needed equipment will be acquired through the procurement mechanism established by this JCPOA. For 15 years, Iran will develop, acquire, build, or operate hot cells (containing a cell or interconnected cells), shielded cells or shielded
glove boxes with dimensions beyond 6 cubic meters in volume and specifications set out in Annex I of the Additional Protocol, only after approval by the Joint Commission.
22. The E3/EU+3 are ready to facilitate all of the destructive and non-destructive examinations on fuel elements and/or fuel assembly prototypes including PIE for all fuel fabricated in or outside Iran and irradiated in Iran, using their existing facilities outside Iran. Except for the Arak research reactor complex, Iran will not develop, build, acquire or operate hot cells capable of performing PIE or seek to acquire equipment to build/develop such a capability, for 15 years.
23. For 15 years, in addition to continuing current fuel testing activities at the TRR, Iran will undertake non-destructive post irradiation examination (PIE) of fuel pins, fuel assembly prototypes and structural materials. These examinations will be exclusively at the Arak research reactor complex. However, the E3/EU+3 will make available their facilities to conduct destructive testing with Iranian specialists, as agreed. The hot cells at the Arak research reactor in which non-destructive PIE are performed will not be physically interconnected to cells that process or handle materials for the production of medical or industrial radioisotopes.
24. For 15 years, Iran will not engage in producing or acquiring plutonium or uranium metals or their alloys, or conducting R&D on plutonium or uranium (or their alloys) metallurgy, or casting, forming, or machining plutonium or uranium metal.
25. Iran will not produce, seek, or acquire separated plutonium, highly enriched uranium (defined as 20% or greater uranium-235), or uranium-233, or neptunium-237 (except for use as laboratory standards or in instruments using neptunium-237) for 15 years.
26. If Iran seeks to initiate R&D on uranium metal based TRR fuel in small agreed quantities after 10 years and before 15 years, Iran will present its plan to, and seek approval by, the Joint Commission.
F. ENRICHMENT CAPACITY
27. Iran will keep its enrichment capacity at no more than 5060 IR-1 centrifuge machines in no more than 30 cascades in their current configurations in currently operating units at the Natanz Fuel Enrichment Plant (FEP) for 10 years.
28. Iran will keep its level of uranium enrichment at up to 3.67 percent for 15 years.
29. Iran will remove the following excess centrifuges and infrastructure not associated with 5060 IR-1 centrifuges in FEP, which will be stored at Natanz in Hall B of FEP under IAEA continuous monitoring:
29. All excess centrifuge machines, including IR-2m centrifuges. Excess IR-1 centrifuges will be used for the replacement of failed or damaged centrifuges of the same type on a one-for-one basis.
29. UF6 pipework including sub headers, valves and pressure transducers at cascade level, and frequency inverters, and UF6 withdrawal equipment from one of the withdrawal stations, which is currently not in service, including its vacuum pumps and chemical traps.
30. For the purpose of this Annex, the IAEA will confirm through the established practice the failed or damaged status of centrifuge machines before removal.
31. For 15 years, Iran will install gas centrifuge machines, or enrichment-related infrastructure, whether suitable for uranium enrichment, research and development, or
stable isotope enrichment, exclusively at the locations and for the activities specified
under this JCPOA.
G. CENTRIFUGES RESEARCH AND DEVELOPMENT
32. Iran will continue to conduct enrichment R&D in a manner that does not accumulate enriched uranium. For 10 years and consistent with its enrichment R&D plan, Iran's enrichment R&D with uranium will only include IR-4, IR-5, IR-6 and IR-8 centrifuges. Mechanical testing on up to two single centrifuges for each type will be carried out only on the IR-2m, IR-4, IR-5, IR-6, IR-6s, IR-7 and IR-8. Iran will build or test, with or without uranium, only those gas centrifuges specified in this JCPOA.
33. Consistent with its plan, Iran will continue working with the 164-machine IR-2m cascade at PFEP in order to complete the necessary tests until 30 November 2015 or the day of implementation of this JCPOA, whichever comes later, and after that it will take these machines out of the PFEP and store them under IAEA continuous monitoring at Natanz in Hall B of FEP.
34. Consistent with its plan, Iran will continue working with the 164-machine IR-4 cascade at PFEP in order to complete the necessary tests until 30 November 2015 or the day of implementation of this JCPOA, whichever comes later, and after that it will take these machines out of the PFEP and store them under IAEA continuous monitoring at Natanz in Hall B of FEP.
35. Iran will continue the testing of a single IR-4 centrifuge machine and IR-4 centrifuge cascade of up to 10 centrifuge machines for 10 years.
36. Iran will test a single IR-5 centrifuge machine for 10 years.
37. Iran will continue testing of the IR-6 on single centrifuge machines and its intermediate cascades and will commence testing of up to 30 centrifuge machines from one and a half years before the end of year 10. Iran will proceed from single centrifuge machines and small cascades to intermediate cascades in a logical sequence.
38. Iran will commence, upon start of implementation of the JCPOA, testing of the IR-8 on single centrifuge machines and its intermediate cascades and will commence the testing of up to 30 centrifuges machines from one and a half years before the end of year 10. Iran will proceed from single centrifuges to small cascades to intermediate cascades in a logical sequence.
39. For 10 years, Iran, consistent with the established practice, will recombine the enriched and depleted streams from the IR-6 and IR-8 cascades through the use of welded pipework on withdrawal main headers in a manner that precludes the withdrawal of enriched and depleted uranium materials and verified by the IAEA.
40. For 15 years, Iran will conduct all testing of centrifuges with uranium only at the PFEP. Iran will conduct all mechanical testing of centrifuges only at the PFEP and the Tehran Research Centre.
41. For the purpose of adapting PFEP to the R&D activities in the enrichment and enrichment R&D plan, Iran will remove all centrifuges except those needed for testing as described in the relevant paragraphs above, except for the IR-1 cascade (No. 1) as described below. For the full IR-1 cascade (No. 6), Iran will modify associated infrastructure by removing UF6 pipework, including sub-headers, valves and pressure transducers at cascade level, and frequency inverters. The IR-1 cascade (No. 1)
centrifuges will be kept but made inoperable, as verified by the IAEA, through the removal of centrifuge rotors and the injection of epoxy resin into the sub headers, feeding, product, and tails pipework, and the removal of controls and electrical systems for vacuum, power and cooling. Excess centrifuges and infrastructure will be stored at Natanz in Hall B of FEP under IAEA continuous monitoring. The R&D space in line No. 6 will be left empty until Iran needs to use it for its R&D programme.
42. Consistent with the activities in the enrichment and enrichment R&D plan, Iran will maintain the cascade infrastructure for testing of single centrifuges and small and intermediate cascades in two R&D lines (No. 2 and No. 3) and will adapt two other lines (No. 4 and No. 5) with infrastructure similar to that for lines No. 2 and No. 3 in order to enable future R&D activities as specified in this JCPoA. Adaptation will include modification of all UF6 pipework (including removal of all sub headers except as agreed as needed for the R&D programme) and associated instrumentation to be compatible with single centrifuges and small and intermediate cascade testing instead of full scale testing.
43. Consistent with its plan and internationally established practices, Iran intends to continue R&D on new types of centrifuges through computer modelling and simulations, including at universities. For any such project to proceed to a prototype stage for mechanical testing within 10 years, a full presentation to, and approval by, the Joint Commission is needed.